12.Notes Payable
On May 13, 2013, the Company entered into a bridge loan agreement (the "Bridge Loan") with RMBAH. The Bridge Loan was in the amount of $5.0 million and was funded on May 14, 2013. The Bridge Loan provided interim working capital for Lost Creek project development prior to receiving funds to be provided by either the State of Wyoming or the RMBAH loan facility discussed below. The Bridge Loan provided for interest at 7.5% per annum in addition to a 4% origination fee all of which was capitalized as construction period borrowing cost. The Company was required to repay the Bridge Loan upon receipt of funds from any source in an amount exceeding $6.0 million or at the maturity date of July 31, 2013. Accordingly, the Bridge Loan was repaid with proceeds from the senior secured loan facility (the “First Loan Facility”) described below.
On June 24, 2013, the Company entered into a $20.0 million First Loan Facility with RMBAH. The First Loan Facility was intended to fund the acquisition and advancement of the Pathfinder assets in Wyoming, and provide other interim Lost Creek development costs pending final approval of the State Bond Loan discussed below. The First Loan Facility was fully drawn as of June 30, 2013 and carried interest at 7.5% plus the three month LIBOR rate recalculated at the start of each calendar quarter, approximately 7.77%. In addition, the Company issued 4,294,167 warrants at an exercise price of Cdn$1.20 per common share with a three-year expiry. Using the Black-Scholes calculations as discussed in note 18, the warrants were calculated to have a value of approximately $3.1 million. The Company also paid an arrangement fee of 6% ($1.2 million) and legal fees to RMBAH totaling approximately $0.2 million. The total effective interest rate on the First Loan Facility is 21.6%. The loan was repaid on October 23, 2013 from the proceeds of the State Bond Loan, however, up to $5.0 million was available to the Company to be redrawn for the purpose of acquiring Pathfinder.
The repayment created a loss from the early extinguishment of debt of $4,032 from the write-off of unamortized deferred loan costs. This amount was redrawn on December 19, 2013 for the acquisition of Pathfinder. The interest rate was approximately 7.75%. Principal payments of $1.25 million each are due quarterly commencing on March 31, 2014. On March 14, 2014, the loan was amended to change the interest rate, extend the loan maturity date to March 31, 2016 and increase the current loan to $10.0 million which included an additional line of credit of $3.5 million as a result of the completion and results of the Technical Report (NI 43-101) on the newly-acquired Shirley Basin property. On March 14, 2014, the Company also drew down an additional $1.5 million on its First Loan Facility. On September 19, 2014, the Company drew down the $3.5 million line of credit. The amended interest rate is approximately 8.75%. Principal payments of $0.81 million are due quarterly.
In August 2013, the Company entered into a $15.0 million second loan facility (the “Second Loan Facility”) with RMBAH. This Second Loan Facility was intended to allow the Company to complete the construction of the Lost Creek facility pending the approval and funding of the State Bond Loan discussed below. In addition, the Company issued 3,100,800 warrants at an exercise price of Cdn$1.25 per common share and a three-year expiry. Using the Black-Scholes calculations as discussed in note 18, the warrants were calculated to have a value of approximately $1.1 million. The Company also paid an arrangement fee of 6% ($0.9 million) and legal fees to RMBAH totaling approximately $0.1 million. The total effective interest rate on the Second Loan Facility is 16.1%. The loan was repaid on October 23, 2013 from the proceeds of the State Bond Loan. The repayment created a loss from the early extinguishment of debt of $1,622 from the write-off of unamortized deferred loan costs. At that time, one half (1,550,400) of the warrants were cancelled per terms of the facility.
On October 15, 2013, the Sweetwater County Commissioners approved the issuance of a $34.0 million Sweetwater County, State of Wyoming, Taxable Industrial Development Revenue Bond (Lost Creek Project), Series 2013 (the “Sweetwater IDR Bond”) to the State of Wyoming, acting by and through the Wyoming State Treasurer, as purchaser. On October 23, 2013, the Sweetwater IDR Bond was issued and the proceeds were in turn loaned by Sweetwater County to Lost Creek ISR, LLC pursuant to a financing agreement dated October 23, 2013 (the “State Bond Loan”). The State Bond Loan calls for payments of interest at a fixed rate of 5.75% per annum on a quarterly basis commencing January 1, 2014. The principal is payable in 28 quarterly installments commencing January 1, 2015 and continuing through October 1, 2021. The State Bond Loan is collateralized by all of the assets at the Lost Creek Project. As a condition of the financing, the RMBAH First and Second Loan Facilities together with certain construction equipment loans were paid off with the funding proceeds from the State Bond Loan.
Deferred loan fees includes legal fees, commissions, commitment fees and other costs associated with obtaining the various financings. Those fees amortizable within 12 months of the statement date are considered current assets. Interest expense in 2013 includes a loss of $5,654 from the early extinguishment of the RMB First and Second Loan Facilities due to the write-off of unamortized deferred financing costs.
The following table lists the current and long term portion of each of the Company’s debt instruments at December 31, 2014 and December 31, 2013:
Schedule of payments on outstanding debt as of December 31, 2014:
|